Project: EPCM Rincon Rapid 3ktpa Li2CO3 Plant
Client: Rincón Mining Pty Limited – Sucursal Argentina

Localización: Salta, ARGENTINA

Description:
The project is located in the elevated region and in the Puna, at 3,800 m above sea level, located 270 km west of the city of Salta. Rio Tinto is looking to develop the deposit to extract boric acid and lithium products, as well as a byproduct of sodium sulfate. The scope includes the installation of all structural steel, mechanical equipment, piping, E&I (SMPEI) works associated with Project R3000. In addition, Contreras is also responsible for pre-commissioning, commissioning and commissioning.


Execution Period: september 2023 - in execution